It’s the first question every client asks, and the one contractors are most afraid to answer honestly. Here it is: a typical full bathroom renovation takes about two weeks from first hammer swing to final caulk line — 7 to 10 working days. A smaller refresh can come in under that. Moving walls or drains stretches it. Here’s where those days actually go.
Day 1 — Demolition
Out comes the old tub or shower, toilet, vanity, flooring, and tile — down to studs and subfloor wherever the new work is going. Debris leaves with us the same day. Demo day is also discovery day: this is when everyone finds out what’s been hiding behind the walls for the last 30 years.
Days 2–3 — Rough work and waterproofing
Plumbing gets moved or renewed where the new layout needs it, any tired subfloor gets repaired, and the new tub or shower base goes in. Then the Schluter waterproofing system goes on the shower walls. This is the unglamorous work nobody photographs — and the work the whole renovation depends on, because everything after it assumes it was done right.
Days 3–5 — Tile
Floor tile first (with the heated-floor cable laid before it, if you’ve added one), then the shower or tub surround. Large-format tile covers ground quickly but every piece still has to be set, levelled, and left to cure. Intricate patterns and small mosaics take longer — there’s no honest way around that, and anyone who quotes you tile like it’s all the same is guessing.
Day 6 — Grout
Grout day looks quick and isn’t. The grout goes in, gets cleaned, and then it needs cure time before fixtures land against it. Some days in a renovation are short because the materials say so — thinset and grout cure on chemistry’s schedule, not ours. A contractor who rushes cure times is borrowing from your renovation’s lifespan.
Days 7–9 — Fixtures and finishes
The vanity goes in, toilet gets set, faucets and shower trim go on, then the mirror, towel bars, and accessories. Walls get their final paint, the last silicone lines go down, and everything gets cleaned and tested. This is the part where it stops looking like a job site and starts looking like your bathroom.
The one exception: shower glass
If your shower gets a glass door, here’s the industry’s worst-kept secret: the glass is measured after the tile is finished, because the opening has to be measured exactly as built, not as planned. Tempered glass then takes roughly two to four weeks to fabricate. So the bathroom is complete and usable, and the glass lands shortly after. Every reputable renovator works this way — if someone promises your custom glass will be ready the day the tile is done, they measured early and you’ll find out why that’s a problem.
The honest summary: most of our full bathrooms run 7 to 10 working days of actual work. Spread over two calendar weeks, that leaves room for grout and thinset to cure properly — and for us to do it once, properly, instead of fast and twice.
What actually slows a renovation down
- Fixtures that aren’t on site. The single most common delay. A vanity or valve that arrives in week two instead of before day one stops everything downstream of it. Our clients order early through our preferred suppliers at wholesale pricing, so the boxes are waiting before we are.
- Surprises behind walls. Rotted subfloor around an old tub and plumbing that predates modern standards are the two classics. They’re fixable — but they’re discovered on day one, not scheduled in advance.
- Moving drains. Swapping a tub for a shower in the same footprint is one thing. Relocating a toilet or drain across the room is another, and it adds real days.
- Decisions made mid-job. Changing tile, fixtures, or layout after demo means re-ordering, waiting, and sometimes re-doing. The time to change your mind is before day one — it’s also the cheapest time.
How to keep yours on schedule
Have everything selected and ordered before demolition starts. Make your decisions up front instead of as the job unfolds. And be a little suspicious of any timeline that sounds too good — we’d rather quote you two honest weeks and finish in ten days than promise one week and still be in your hallway in week three.